a. Owner has 21
days to correct.
b. Owner may seek
2 postponements if pending capital work.
c. May grant
longer postponement if pending capital work.
d. Certifications
must be submitted within 5 days of correction date.
e. HPD must
re-inspect all violations within 14 days.
f. ERP must
correct within 45 days where owner fails to do work.
I. HPD may not remove any violations
from its records unless it has conducted a final inspection verifying
remediation, and has copies of relevant dust test.
II. HPD must mail
a copy of the final inspection report and status to the occupant and
owner.
|
a.
Commissioner’s Order To Abate
|
a) If DOHMH
issues a COTA – Commissioner’s Order to Abate for a lead poisoned child
in a multiple dwelling within 15 days, HPD must notify the owner to
submit to HPD all records of notification & investigation within 45
days.
b) If records
show there may be lead hazards in other units with children under age 7,
HPD will inspect all such units within 10 days.
c) If the owner
does not provide the records, HPD must attempt to inspect child occupied
units in 45 days to determine if there are any lead violations.
d) The actions
required of HPD are not applicable if HPD has inspected the building
within the 12 months preceding the issuance of the COTA.
|
|
|
a) Peeling lead
paint is prohibited.
b) Lead hazards
must be remediated.
c) Equipment
must have lead free paint.
d) If
non-complying condition is found, DOHMH must serve the operator with an
order to remediate.
e) If the order
is not complied within 45 days, DOHMH must request an “Agency of the
City” to execute the order.
f) That agency
must execute the order in 45 days.
g) Lead hazards
must be remediated in compliance with DOHMH safe work practices.
|
|